EST / EFT / LST / LFT
Activity time points
The four time points per activity in the network diagram:
- EST – Earliest Start Time
- EFT – Earliest Finish Time
- LST – Latest Start Time
- LFT – Latest Finish Time
Total float = LST − EST (or LFT − EFT).
Activity time points